PROJECT SUMMARY

HWY 32 - WIMBERLY TRANSMISSION

           

COUNTY:

Hays, TX

 

ACQUIRING AUTHORITY:

Pedernales Electric Cooperative Inc

 

PARAMETERS:      

New 138 kV Transmission line from PEC’s existing Hwy 32 substation to it’s existing Wimberly substation in Hays county. A Modified route C has been recommended as the proposed route.

                       

SCHEDULE:

R/W: March 2018 – February 2019

Con: July 2018 – May 2020

 

The Hwy. 32 - Wimberly kV Line will rebuild and upgrade electric transmission lines in Hays County, Texas. Get more details here.

Learn how not to get "taken" when the government takes your land with our free Texas Eminent Domain Guide.