PROJECT SUMMARY
P2K PIPELINE
COUNTIES:
Pecos, Crane, Upton, Reagan, Irion, Schleicher, Menard, McCulloch, San Saba, Burnet, Williamson, Lee, Washington, Austin, Waller, Wharton, TX
ACQUIRING AUTHORITY:
Sempra LNG & Midstream, and Boardwalk Pipeline Partners
PARAMETERS:
The approximately 520-mile, 42-inch and 36-inch pipeline project is proposed to
transport up to 2.25 billion cubic feet per day (Bcfd) of natural gas from Waha Hub Headers in the Permian Basin to Katy and the Houston Ship Channel.
SCHEDULE:
August 2017 – September 2017: Open Season conducted
Q1 2018: Negotiate and sign precedent agreements
Q2 2018: Final Investment Decision
Q3 2020: Operations begin
The P2K Pipeline project will transport natural gas from the Permian Basin to the Texas gulf coast. Get more details here.