PROJECT SUMMARY

PORT ARTHUR RELIABILITY

 

COUNTIES: 

            Jefferson, TX

 

ACQUIRING AUTHORITY:

            Entergy Texas

                                                         

PARAMETERS:

A new 230 kV Transmission line in Jefferson County between the proposed new Garden substation located SW of Central Gardens to a proposed new Legend substation located SE of Port Acres. Route 11 is the chosen route.

 

SCHEDULE:

RW March 2018 - February 2019

Construction July 2018 - May 2020

 

The Port Arthur kV Line project will connect electrical substations in Port Arthur, Texas. Get more details here.